Night Basketball Under the Stars

Acrylic basketball court fully illuminated by LED floodlights at night, Noida residential society

Noida, Uttar Pradesh

8:30 PM. 34 residents on court.
Every evening.

Night photography shown is representational. Actual site imagery will be updated upon client approval.

Noida Uttar Pradesh
7,200
Square Feet — FIBA Court
10
Days to First Night Game
40%
Saved on Base Cost
4×200W
LED Floodlight Arrays
34
Residents Playing Daily
3 Yrs
Surface Warranty
THE CHALLENGE

The existing concrete base had been poured by a previous contractor and then abandoned — the project had run out of money, or out of coordination, the RWA was not entirely sure which. What remained on site was 7,200 sqft of cured M20 grade concrete: solid, flat by eye, and missing everything above it. The slab had been sitting unfinished for two years. In that time it had become overflow parking, a bicycle storage area, and — by one resident's labrador — a preferred morning circuit.

The RWA had spoken to two vendors before approaching ChampCourts. The first recommended full demolition — no way to guarantee quality acrylic over concrete that had been exposed and stressed for two years. The second said the slab was fine and they could coat it directly. Both answers were incomplete. Neither vendor had taken a level reading.

ChampCourts brought a laser level. The reading across the 120-foot length of the court showed a 1.8-degree slope — roughly 3.7 feet of elevation difference from one baseline to the other. Not visible to the eye. But significant enough to affect ball bounce, shot angles, and the strain on players who are always running slightly uphill in one direction. The slab was not broken. It just needed a levelling correction before any coating could go on.

Laser level survey identifying the 1.8-degree slope in the existing concrete base
Laser level survey — the 1.8-degree slope measured and documented across the court's long axis. This reading changed the scope and saved the society Rs 6.48 lakh.

The society also had a requirement that no previous contractor had been asked to address: night play. Most residents in this society finish their working day at 6 PM. Morning slots were theoretically available but practically useless for anyone on a standard office schedule. The court needed proper floodlighting — not decorative perimeter bollards, but professional-grade coverage calibrated for basketball. That means uniform lux across the full 7,200 sqft with no shadows in the three-point arc.

"Two years of waiting. Two vendors who never measured anything. And then someone finally turned up with a laser level. That was the moment we knew we had found the right team."

RWA Sports Committee Chairperson, A Residential Society, Noida
THE SOLUTION

The proposal was straightforward: retain the existing base, correct the slope with an acrylic-modified levelling compound, then apply the full 8-layer acrylic system over the corrected surface. The saving against a demolish-rebuild was Rs 6.48 lakh — the cost of new M20 concrete and GSB sub-base across 7,200 sqft that simply was not needed. The RWA committee approved the proposal the same evening it was presented.

The colour specification was Royal Blue for the main court area and Light Blue for the run-off perimeter and key zones. This two-tone combination does several things at once: it creates a clear visual boundary between court and surround, it looks outstanding under 5000K floodlights (neutral white, which is the right colour temperature for court sports lighting), and it gives the court a professional appearance that photographs well at any time of day or night.

The lighting design was four 200W LED flood arrays on galvanised steel poles at the four corners of the court, aimed inward and downward at angles calculated to give uniform coverage across the full playing surface. The critical challenge in corner-lit setups is the three-point arc — the zone most exposed to shadow on standard four-corner installations. The pole height and flood-head angle here were specified specifically to eliminate that shadow.

LED floodlight layout plan showing four corner poles with overlapping coverage zones
LED layout — four 200W arrays at the four court corners. The pole angle was calculated to eliminate shadow at the three-point arc, the zone most exposed on standard corner-lit configurations.
8-Layer Acrylic System ₹65/sqft Existing Base Retained + Slope Corrected Acrylic Levelling Compound Royal Blue + Light Blue FIBA Basketball Markings 4 × 200W LED Flood Arrays 5000K Colour Temperature 3-Year Surface Warranty
Planning a Similar Basketball Court?
Tell us about your space, sport, and timeline. We'll send you a detailed estimate within 48 hours — completely free.
Get Free Estimate WhatsApp Us
Free estimate • No commitment • Response within 48 hours
THE BUILD

The team arrived on Day 1 with the laser level results already converted into a levelling compound pour plan. The slope correction was the first task — the most technically demanding — and everything else depended on getting it right. Until the base was flat, no coating work could begin.

Day 1
Laser Survey Verification + Surface Preparation
Full laser level grid survey across the 7,200 sqft slab — 48 measurement points. Slope confirmed: 1.8 degrees, running east to west across the long axis. Slab pressure-washed, cracks mapped (none significant), surface diamond-ground lightly to open pores for bonding. LED pole foundation pits marked at the four court corners.
Days 2–3
Levelling Compound Pour
Acrylic-modified self-levelling screed poured across the low end of the court in controlled sections, feathering to zero at the high end. Laser-checked at 4-hour intervals during cure. By Day 3 morning, the surface read ±2mm deviation across the full 120 ft × 60 ft — within FIBA tolerance for new court construction. The slope that had made two years of play impossible was gone. LED pole foundations concrete-poured on Day 3 afternoon.
Day 4
Primer + Acrylic Resurfacer (Layer 1)
Full surface primed with acrylic bonding primer. Layer 1 (acrylic resurfacer) applied by a roller team of ten across the full 7,200 sqft in a single session starting at 5:30 AM — to finish before Noida's afternoon heat peaked. Surface inspected for pinholes and coverage gaps before calling the layer complete.
Days 5–7
Sand Binder + Base Coats (Layers 2–5)
Layer 2 (sand-filled acrylic binder) applied for surface grip — the texture layer that governs bounce consistency and foot traction. Layers 3–5 (build-up and filler coats) applied in sequence with 24-hour minimum cure between each. Each layer checked for uniformity before proceeding. Light Blue key zone boundaries masked on Day 7 afternoon in preparation for the colour separation.
Days 8–9
Royal Blue + Light Blue Colour Coats (Layers 6–7) + LED Poles
Royal Blue applied to the main court zone on Day 8. Light Blue applied to the run-off perimeter and key zones that same afternoon in a separate session after masking the Royal Blue boundary. Layer 7 finish coat on Day 9 morning across both colour zones. LED poles installed in their cured concrete foundations Day 9 afternoon — base plates bolted, poles plumbed, electrical conduit run underground from the society's distribution board.
Day 10
FIBA Markings, Floodlight Commission + Night Test
Layer 8 (UV-resistant final finish coat) applied early morning. White FIBA markings — three-point arc, key, free-throw line, centre circle, half-court line — applied at midday, all dimensions checked against FIBA standard. LED flood arrays mounted and aimed by 4 PM. Circuit commissioned by a licensed electrician. Night test at 8 PM — lux readings taken at 12 points across the court. Uniform coverage confirmed: no shadow in the three-point arc. Basket posts installed. Six residents played the first pickup game under the new lights.
Acrylic-modified levelling compound being poured to correct the slope in the existing slab
Day 2 — levelling compound going in. The screed is feathered over 120 feet, thick at the low end, tapering to zero at the high end. The laser checks every 4 hours.
Royal Blue acrylic colour coat being applied by roller team on Day 8
Day 8 — Royal Blue colour coat. The key zone is already masked. Light Blue follows this afternoon after the boundary tape comes off.
LED floodlight poles being installed in foundation pockets on Day 9
Day 9 — LED poles in. Conduit run underground from the society DB board. Flood arrays mount tomorrow morning. Commissioning at 8 PM.
First night basketball session under LED floodlights on the completed Noida court
Day 10, 8:10 PM — first pickup game on the new court. Six residents. Four floodlights. No shadow in the three-point arc. Lux reading within specification at all twelve test points.

All images are illustrative placeholders. Final installation photographs and night photography pending client approval.

Want to see what this would cost for your space?
Get Estimate Call Now WhatsApp
THE RESULT

The society's parking areas — which had become the default social gathering spot for working-age residents — quietly became secondary. The court was better. In the first full week of operation, 34 unique residents played at least once. By the third week, the court had a booking request system — not because the RWA set one up, but because residents had worked it out among themselves. Some organisation was needed to ensure fair access to the evening slots.

A kids' weekend coaching programme started in the sixth week, run informally by a resident who had played club basketball in college and had been looking for the right opportunity to pass on the game. Eight children enrolled in the first batch. The RWA provided two basketballs. The coach brought two more. The programme started on Saturday mornings and moved to Sunday as well when Saturday filled up.

The Rs 6.48 lakh saving from retaining and correcting the existing base was reallocated by the RWA committee. Half funded the LED floodlight installation. The other half went into the society's maintenance reserve. The sports committee chairperson noted at the following AGM that the basketball court had returned more in community engagement than any other capital expenditure in the society's recent history. The previous contractor had left a slab. ChampCourts made it a court. The floodlights made it a community.

A Slab, a Slope Correction, and a Community That Comes Alive After Dark.
34
Residents Playing Daily
₹6.48L
Saved vs. Full Demolish-Rebuild
10
Days to First Night Game
1
Kids' Weekend Coaching Batch Started
Project delivered in 10 days — Day 10 evening: first pickup game under lights
Evening court slot utilisation at 60 days — 87% of 6 PM–10 PM hours booked
Lux uniformity test — uniform coverage at all 12 test points, zero shadow in three-point arc

"We had been looking at that unfinished slab for two years. The question was never whether to build the court — it was whether to trust someone to do it properly. These people measured first. That made all the difference."

RWA Sports Committee Chairperson, A Residential Society, Noida
Product specifications: 8-Layer Acrylic Coating at ₹65/sqft. Existing slab retention subject to prior structural and level assessment — suitability determined case-by-case. Cost savings are project-specific; the Rs 6.48 lakh figure reflects this specific installation and should not be assumed for other projects without an independent assessment. 3-year surface warranty, 5–7 year lifespan under normal outdoor conditions. LED floodlight specifications vary by site — lighting design requires separate consultation. All project details shared with RWA consent. Society name withheld at client request.

Want a Court Like This?

Tell us about your space, your sport, and your timeline. We'll send you a detailed estimate within 48 hours — completely free.

  • Free estimate — no commitment
  • Written quote within 48 hours
  • Turnkey delivery across India

Prefer to call or WhatsApp?

Get Your Free Estimate

We respond within 24 hours. No spam, no pressure.