Building Through the Rain

Dark monsoon clouds gathering over the Tezpur school site before construction
Late June, Tezpur — the monsoon and the tiles arrived in the same week. Assam gets up to 3,500mm of rain a year. Most of it had strong opinions about our schedule.
Material truck on NH-15 through Assam plains heading to Tezpur
The material truck crossed a Brahmaputra tributary by ferry — 2,500 km from Dehradun. One of those crossings meant an 11-hour wait at the waterline.
Green PP tile installation in progress between rain events
Day 12 — tiles going in between showers. The crew learnt to read the sky as carefully as the tile grid. Every dry window was used fully.
Tezpur Assam
3,500
Square Feet Installed
28
Days (3 Rain Delays)
2,500
km From Dehradun HQ
Green + Blue
PP Tile Colours
40
Years — School's History
15 Yrs
PP Tile Lifespan
THE CHALLENGE

This school had been running on the banks of the Brahmaputra valley for forty years. Management had changed, the curriculum had changed, even the colour on the boundary wall had changed a few times. But one thing had never changed — there was no proper sports court. PE classes happened on packed red earth. Fine when dry. A complete mess when the monsoon hit — and in Assam, the monsoon hits hard for roughly five months of the year.

When the principal finally got a capital improvement fund approved in late spring, she started calling vendors. Most did the math quickly: Tezpur, Assam, pre-monsoon season, smallish project. Two said no outright. A third sent a quote so loaded with logistics surcharges that it ate up more than half the budget. ChampCourts quoted honestly, visited the site, and agreed to proceed. The understanding was clear from day one — this would be built during monsoon season, and the plan had to account for that.

The logistics were tough even without the rain. The nearest major PP tile stockist was 1,400 km away. Getting two full pallets of tiles and kerbing hardware to a school off NH-15 in Assam meant a river crossing, a narrow approach road, and a gate the material truck cleared with eight centimetres to spare. The driver measured this out loud before attempting the turn. The project manager noted that as a sign of a professional who takes his work seriously.

"When they said they'd come all this way and work through the rain, honestly, I did not fully believe them. Then the tiles started arriving."

Principal, A Senior Secondary School, Tezpur, Assam
THE SOLUTION

PP interlocking tiles were the only surface that made sense for a monsoon-season build. Acrylic coating needs 72 hours of dry conditions per application cycle — something you simply cannot guarantee in Assam in June. PP tiles are different. They can be installed in ambient humidity, stopped at any point without damage, and resumed within hours of the rain stopping. A half-finished tile court under a tarpaulin loses nothing during a rain delay. In fact, the snap-fit joints tighten with repeated thermal cycling rather than loosening.

Colour selection came down to availability and function. Green for the basketball court — it reads well against Assam's red soil boundary and photographs cleanly even in flat monsoon light. Blue for the two badminton courts — BWF badminton players respond well to the blue-and-white contrast for court markings, and having two different colours makes it immediately clear which court is which.

The campus had space for a practice-sized basketball court and two compact badminton courts — not full regulation, but perfectly suited to the school's PE curriculum and intramural games. The layout was planned around what the site could actually give us, not what a standard spec sheet assumes.

Drainage was the most important sub-surface decision. The cleared site had a natural 1.8 cm fall across its 60-foot span. That fall was graded and preserved during sub-base compaction — enough to ensure sheet drainage within minutes of rain stopping. Three perimeter channels were installed on the low side to intercept surface water before it could reach the building wall.

Sub-base grading and perimeter drainage channel installation at the Tezpur site
Sub-base grading and drainage channels — done before the first tile was touched. In monsoon Assam, if your drainage is not right, nothing above it will be either.
PP Interlocking Tiles ₹70/sqft Green — Practice Basketball Court (1,750 sqft) Blue — Badminton Courts (2 × 875 sqft) 3,500 sqft Total Surface Monsoon-Rated Sub-base + Drainage 170 Basketball Kerbs + 4 Corners 250 Badminton Kerbs + 8 Corners 5-Year Warranty
Planning a Similar Multi-Sport Court?
Tell us about your space, sport, and timeline. We'll send you a detailed estimate within 48 hours — completely free.
Get Free Estimate WhatsApp Us
Free estimate • No commitment • Response within 48 hours
THE BUILD

The material truck left on a Tuesday. Three state borders, an 11-hour wait at a Brahmaputra tributary crossing for the ferry to return from an upstream commercial run, and it arrived on site on Day 4. The crew of seven — who had flown into Guwahati and come overland to Tezpur — were already there. They had spent Day 3 grading the sub-base and putting in the drainage channels. When the tiles arrived, the site was ready for them.

Days 1–3
Sub-base Grading, Compaction & Drainage
The earth surface was levelled and graded to preserve the natural 1.8 cm drainage fall. Sub-base compacted in two lifts with a plate compactor. Three perimeter drainage channels excavated and cast in concrete on the low side. A light rain on Day 2 gave us an unplanned drainage test — water cleared the site in 18 minutes. The crew called it the most useful test of the whole project.
Days 4–9
Material Arrival + Basketball Court Grid Begins
Tiles unloaded and stacked under tarpaulin, colour-sorted. Basketball court reference grid set with strings. Green tile installation started from the south baseline moving north. Day 7 brought six hours of rain and a work stoppage — but the crew used that window to pre-stack tile rows in the correct installation sequence, so when the rain stopped they could go straight back to full speed without any warm-up time.
Days 10–17
Basketball Court Completed + First Rain Delay
Green tiles completed, perimeter kerbs fitted, corner pieces secured. Basketball markings painted on Day 14 during a clear-sky window. The second rain delay came on Day 15 — 22 hours straight. No tile damage. The snap-fit joints held, and standing water drained from the completed section within 25 minutes of rain stopping. One tile near the north baseline had slightly lifted due to sub-surface water pressure. Re-seated, no replacement needed.
Days 18–24
Badminton Courts — Blue Tile Installation
Both badminton courts installed simultaneously with a split crew, each team working from their own south baseline. The third and longest rain delay hit on Day 21 — 38 hours of continuous rain. Rather than going back to town, the crew stayed on site in a school outbuilding. That meant they could resume within the hour of rain stopping. BWF court markings painted Day 24.
Days 25–28
Kerbs, Net Posts, Final Inspection & Handover
Badminton perimeter kerbs and corner pieces fitted. Basketball goals and badminton net posts installed and anchored. Full joint inspection — every kerb seam and tile connection checked by hand. Zero failures. Perimeter drainage channels cleared of construction debris and tested with a water pour. Court handed over Day 28. The annual sports day was moved forward. It rained during the opening ceremony. The courts drained in twenty-two minutes and play went on.
Sub-base compaction during early site preparation in Tezpur
Day 2 — sub-base compaction. The drainage fall is graded in at this stage. It cannot be corrected after the tiles go down.
Green PP tile basketball court installation nearing completion
Day 12 — Green basketball court three-quarters done. The school's first proper court surface was taking shape, despite the sky's best efforts.
Both Blue badminton courts being installed simultaneously by split crew
Day 20 — both Blue badminton courts going in together. Split crews from opposite baselines. Everything was running in parallel.
Completed multi-sport courts on Day 28 — basketball and both badminton courts
Day 28 — handover. The school's first proper sports surface in 40 years. Built through 3 monsoon stoppages, 2,500 km from base.

All images are illustrative placeholders. Final installation photographs will be updated upon client approval.

Want to see what this would cost for your space?
Get Estimate Call Now WhatsApp
THE RESULT

For thirty-nine years, the annual sports day had been held on packed earth — boundaries marked in lime powder that smudged in the first light rain. This year, students competed on Green and Blue PP tiles. When the rain arrived mid-afternoon, everyone treated it as an intermission rather than a cancellation. The courts drained. Play resumed in under half an hour.

Six weeks after installation, the school held its first inter-school tournament. Four institutions from across Sonitpur district sent teams for the basketball competition. A crowd assembled on this campus that had not been seen here for any non-academic occasion in living memory. Parents who had driven in from distant villages stood at the boundary wall watching their children play on a surface that, a month earlier, had not existed.

The PE department launched a structured coaching programme in the weeks that followed — something that had simply not been possible without a surface that could hold markings, take lateral cuts, and survive northeast India's rainfall. The three rain stoppages during construction turned out to be the best possible advertisement. If PP tiles could handle the Assam monsoon during installation itself, they would clearly handle it in service.

2,500 km. 28 Days. 3 Delays. The School's First Court.
40
Years — First Proper Sports Surface
4
Schools in First Inter-School Tournament
3,500
sqft of All-Weather Surface
0
Tiles Replaced After Monsoon Delays
Project completed on deadline despite 3 rain stoppages totalling 66+ hours
Court utilisation at 60 days — 88% of available hours in active use
Post-monsoon tile inspection — 95%+ of tiles checked, zero replacements required

"I have seen contractors walk away from far less. These men stayed, worked in every window between the rains, and gave us something this school has never had. I don't have a better word for it than commitment."

Principal, A Senior Secondary School, Tezpur, Assam
Product specifications: PP Interlocking Tiles at ₹70/sqft (supply). Kerbs at ₹25/piece, corners at ₹15/piece. 5-year warranty, 15+ year lifespan. Colors subject to availability; made-to-order colors carry a 14-day lead time. Court dimensions and configuration vary by site. Drainage design is site-specific and assessed individually. All project details shared with client consent. Institution name withheld at client request.

Want a Court Like This?

Tell us about your space, your sport, and your timeline. We'll send you a detailed estimate within 48 hours — completely free.

  • Free estimate — no commitment
  • Written quote within 48 hours
  • Turnkey delivery across India

Prefer to call or WhatsApp?

Get Your Free Estimate

We respond within 24 hours. No spam, no pressure.