The School That Said 'Cricket AND Basketball'

Phase 1 — Basketball (PP Tiles) Phase 2 — Cricket (Artificial Turf)
Blue PP tile basketball court — Phase 1 completion Artificial turf cricket pitch — Phase 2 completion
Lucknow, Uttar Pradesh
North India — Phased delivery across 35 days

The sports committee meeting lasted two hours and forty minutes, by the principal's own account. On one side: the cricket coaching staff, who had been asking for a proper pitch surface for three years. On the other: the basketball programme, which had just produced two players shortlisted for inter-school district trials — and needed a regulation court before the tournament in six weeks.

The principal made a call that both sides initially viewed with suspicion: both. The school's 11,400 sqft sports area would carry a basketball court at one end and a cricket pitch at the other. Two surfaces. Two different systems. One phased project that had to deliver Phase 1 within 18 days or the basketball team missed their tournament.

Our proposal was straightforward: build the basketball court first, completely, before a single roll of cricket turf is unloaded. The cricket coaching staff were not happy about going second. But they understood why.

11,400 sqft
Total Area — Both Surfaces
📅
35 days
Total Duration (Phased)
🏈
7,200 sqft
Basketball — PP Tiles
🏺
4,200 sqft
Cricket — Artificial Turf
₹16L
Combined Investment
🏆
2x
Sports Scholarship Students

The Challenge

Two different sport surfaces on one campus — that is not primarily a construction challenge. It is a sequencing, logistics, and stakeholder management challenge. With a hard deadline sitting right in the middle of it.

The basketball court needed PP interlocking tiles on a prepared base. The cricket pitch needed artificial turf with a shock-pad underlayer and infill. These two systems could not overlap or share any materials. The boundary between them — a 6-foot buffer zone that would eventually become a walking pathway — had to be marked from Day 1 so neither installation touched the other's sub-base area.

The deadline pressure was real and there was no room to slip.

The inter-school basketball tournament was confirmed for Day 22 of the project — four days after the basketball court handover was due. That gave the school's PE team two days of practice before hosting. If we handed over on Day 19 instead of Day 18, that buffer shrank to one day. Day 20 and it was gone entirely.

We assigned a dedicated site supervisor to the basketball phase whose only job was the Phase 1 handover date. The cricket pitch team was kept on standby in Lucknow from Day 15 — present but idle — so Phase 2 could start the morning after Phase 1 handover with no mobilisation delay.

Site planning showing the boundary between basketball and cricket zones

There was one more complication. The 11,400 sqft plot had been used as an informal playground for years. Sub-surface compaction was uneven — our site team found two patches in the cricket end where the soil was soft enough to need additional compaction before any base work could begin. We caught this on Day 1 ground assessment and sorted it before the basketball base pour started, so it did not delay Phase 2 later.

The Solution

We mobilised a crew of eight for Phase 1 — double the usual team for a basketball court this size. The logic was simple: a larger crew in Phase 1 creates margin. If you lose a day to weather, a material delay, or a base complication, a bigger team can recover those hours by extending the working day rather than slipping the handover date.

The basketball court was designed in Blue PP tiles — a colour the students had themselves voted for during a short survey the principal ran the week before work started. That survey was the principal's idea, not ours, and it turned out to be smart stakeholder management. Students who had voted for the colour started arriving each morning to watch the progress with genuine personal investment in what was being built.

When the students voted for the court colour, something shifted. They stopped seeing it as a construction project happening near them and started seeing it as their court being built. The energy on campus changed from that day forward.

— The Principal, Lucknow school

The cricket pitch used a 40mm artificial turf pile with a 10mm shock pad — right for a school using the surface for both practice and occasional match conditions. The turf was laid with a polyurethane adhesive seam system and sand infill applied in two passes to reach the correct playing surface firmness. Line marking covered the popping crease, return crease, and batting crease in white boundary tape.

Blue PP Tiles — Basketball Artificial Turf — Cricket PP Tiles @ ₹70/sqft 5-Year PP Warranty 15-Year PP Lifespan 40mm Turf Pile + 10mm Shock Pad Sand Infill — 2-Pass Application
Planning a Similar Sports Court?
Tell us about your space, sport, and timeline. We'll send you a detailed estimate within 48 hours — completely free.
Get Free Estimate WhatsApp Us
Free estimate • No commitment • Response within 48 hours

The Build — Phase by Phase

Day 1
Ground Assessment + Zone Demarcation
Full site survey. Soft patches in the cricket zone identified and compacted. Basketball and cricket boundary marked with chalk and wooden pegs. Sub-surface drainage mapped. Phase 2 standby crew briefed on findings.
Days 2–6 — Phase 1
Basketball Base — GSB + PCC Pour
GSB sub-base laid and compacted in the basketball zone (7,200 sqft). M20 PCC poured in a continuous session. Curing started under shade cover to protect from Lucknow's November sun. Phase 2 crew used this window to finalise cricket sub-base compaction.
Days 7–14 — Phase 1
Basketball Tile Installation
Blue PP tiles installed across 7,200 sqft. Kerbs placed around the full perimeter (360 pieces + 4 corners). Court centre marking and three-point line boundary zones indicated with tile colour contrast at key positions. Court lines taped.
Day 18 — Phase 1 Handover
Basketball Court Delivered
Court handed over to the school. PE teacher ran a supervised trial session. Students played their first practice game on the new court. Phase 2 cricket crew moved in the same afternoon to begin Phase 2 base preparation.
Days 19–29 — Phase 2
Cricket Pitch — Sub-Base + Turf Laying
Sand-compacted base layer for cricket. Shock pad underlayer laid. Artificial turf rolled and seamed. Sand infill applied in two passes over two days. Crease markings applied.
Days 30–35 — Phase 2
Cricket Pitch Finishing + Final Handover
Second infill pass. Batting crease and bowling crease lines checked for regulation compliance. Buffer pathway between the two surfaces finished with compacted gravel. Full site handed over on Day 35.
Completed Blue PP tile basketball court at Lucknow school
Phase 1 complete — basketball court ready on Day 18, four days before the tournament
Completed artificial turf cricket pitch
Phase 2 complete — cricket coaching started on Day 35
Inter-school basketball tournament held at the school's Phase 1 court
The inter-school tournament was hosted on schedule — the school won their first home-court game
Aerial view showing both the basketball and cricket surfaces
Both surfaces complete — 11,400 sqft of multi-sport infrastructure on one campus
Want to see what this would cost for your space?
Get Estimate Call Now WhatsApp

The Result

Phase 1 was delivered on Day 18. The basketball team had their court four days before the tournament. They used that time well. They won their first home-court match of the season. The principal sent us a message that evening. Two words, with a score attached. Those two words were "Thank you."

Phase 2 was handed over on Day 35. The cricket coaching programme started the following Monday with a full batch of students who had, in the principal's words, "been waiting since 2021." In the first academic year after both surfaces were complete, the number of students on sports scholarships had doubled — driven by performances at inter-school tournaments in both basketball and cricket.

The buffer pathway between the two surfaces became something no specification document had planned for. The school placed two benches there, and it became an informal gathering spot for players waiting for their court time. Some things just happen on their own.

What Changed
2x
Sports scholarship students in Year 1
Day 18
Phase 1 delivered — 4 days before tournament
2 Sports
On one campus for the first time
1st
Home-court tournament win, same season

All project photographs shown are representative illustrations. The institution's name and individuals' identities have been withheld to protect client privacy. Timeline data, court dimensions, and financial figures reflect actual project records. Outcome data (scholarship numbers, tournament results) is based on information shared by the principal over the subsequent academic year.

Want a Court Like This?

Tell us about your space, your sport, and your timeline. We'll send you a detailed estimate within 48 hours — completely free.

  • Free estimate — no commitment
  • Written quote within 48 hours
  • Turnkey delivery across India

Prefer to call or WhatsApp?

Get Your Free Estimate

We respond within 24 hours. No spam, no pressure.