The IT Park That Became a Sports Hub

On Day 1, before a single tile had arrived, we mounted a timelapse camera to a structural column at the north end of the space. Frame interval: fifteen minutes. Over the next 28 days, it recorded 7,800 square feet of empty ground-floor retail becoming a six-court badminton complex — tile by tile, court by court, from a bare concrete slab with exposed HVAC overhead to a fully lit, acoustically tuned, league-ready sports facility. Compressed to three minutes, it is one of the most satisfying construction sequences we have produced. The IT park uses it as a tenant presentation asset to this day.

7,800
Square Feet Total
28
Days to Handover
6 Courts
Blue + Green + Red
🏢
Corporate
IT Park, Bengaluru
THE SPACE PROBLEM

Ground-floor commercial space in a Bengaluru IT park sounds like a straightforward asset. For this particular property, it had been a slow-burn problem for three years. The 7,800 square feet at the base of Building C had cycled through two food-court operators and a short-lived gym — each leaving a different fitout for the next tenant to gut. The park management had spent more on strip-outs than on any single fitout. By the time ChampCourts was contacted, the space had been sitting empty for eight months. The facilities manager was fielding weekly complaints from 12 companies whose combined 5,000-plus employees had nowhere meaningful to spend their lunch break. Then someone in a committee meeting said the word "badminton."

The word landed. Bengaluru is a badminton city in a way that is difficult to explain to someone who has not worked in its technology sector. Shuttle courts are the office sport the way squash was for a previous corporate generation. Across the park, four companies had internal badminton WhatsApp groups of over a hundred members each. The facilities manager ran a quick survey. 83% of respondents said they would use an on-campus badminton facility at least twice a week. The committee approved the project two weeks later.

The empty IT park retail space before construction, Day 1
Day 1. The timelapse camera is already running on the left column. Eight months of vacancy about to end in 28 days.
THREE TECHNICAL CHALLENGES

Converting commercial retail into a six-court badminton complex is not just a surface project. It is a building systems project that happens to include a surface. Three challenges had to be resolved before tile work could begin.

Ventilation. Badminton shuttlecocks are acutely sensitive to air movement — even a 1.5 m/s lateral draft is enough to make the shuttle behave unpredictably in flight. The existing HVAC was designed for retail comfort, with supply diffusers positioned for occupant coverage, not for controlling airflow at shuttle-flight height. The park's MEP consultant relocated supply diffusers to a high-level perimeter pattern and reduced supply velocity. Result: 24°C thermal comfort maintained without any lateral movement in the play zone.

Lighting. BWF competition standard requires 500 lux minimum at court level with a uniformity ratio of at least 0.6. The retail lighting delivered between 180 and 240 lux at floor level, with hotspots and shadow bands between fixtures. The park's electrical contractor installed 100W LED high-bay fittings at 8-metre centres — 520 lux average across all six courts at handover, uniformity ratio 0.75.

Acoustics. Six simultaneous badminton games in an enclosed space produce a specific and significant noise environment — shuttle impact, footwork, player calls. The empty retail shell measured 2.8 seconds reverberation time, which would have made game communication on adjacent courts very difficult. Ceiling acoustic baffles brought that figure to 1.1 seconds — comfortable for game communication without players having to shout.

MEP coordination planning for the badminton facility
THE COLOUR LOGIC

Six courts in a single enclosed space create a visual organisation problem. A uniform single-colour field of 7,800 square feet would be monotonous, and it would be hard to track from the gallery end which court a rally was happening on. The facilities manager came up with the colour-coding: Courts 1 and 2 in Blue, Courts 3 and 4 in Green, Courts 5 and 6 in Red. Each pair functions as a distinct visual zone, which also maps directly onto league organisation — teams in the Blue bracket, Green bracket, and Red bracket, using the court colour as the primary identifier for fixture scheduling.

It looks obvious after the fact. During the planning phase, it was the facilities manager's idea, proposed in a ten-minute meeting. We implemented it exactly as he described.

PP Interlocking Tiles 6 Courts — 7,800 sqft Blue + Green + Red 924 Kerb Pieces Total 24 Corner Pieces BWF Doubles Dimensions 520 Lux LED Sports Lighting 15+ Yr Tile Lifespan
KERBS AND CORNERS — 6 COURTS

Each badminton court (52ft × 25ft) requires its own complete kerb perimeter: male kerbs = 52 + 25 = 77 pieces, female kerbs = 77 pieces, total per court = 154 kerb pieces + 4 corner pieces. Across six independent courts: 6 × 154 = 924 kerb pieces + 6 × 4 = 24 corner pieces. These are not shared perimeters — each court has its own complete kerb boundary, so any individual court can be isolated, inspected, or retiled without disturbing the courts beside it. At this scale, that independence is an operational requirement, not a preference.

THE TIMELINE
Days 1–5
Substrate Preparation + MEP Coordination
Existing retail fitout stripped. Concrete slab inspected — two areas of surface delamination repaired, full slab ground to ±3mm flatness tolerance. Parallel work front: MEP contractor begins HVAC diffuser relocation and LED high-bay installation. Acoustic baffle subcontractor starts ceiling work in the Red courts zone (Courts 5 and 6).
Days 6–20
PP Tile Installation — All 6 Courts
Courts installed in sequence from north to south, working behind the MEP installation front. Blue courts (1, 2) first, then Green courts (3, 4), then Red courts (5, 6). BWF singles and doubles line markings integrated as tile-colour changes within the lay. Three-person tile crew maintained approximately 600 tiles per day. Total: 7,800 individual 1ft×1ft tiles across all courts.
Days 21–25
Kerbs, Lighting Commissioning, Acoustic Baffles
924 kerb pieces + 24 corner pieces installed across all 6 court perimeters. LED lux measurements taken at 36 positions across the courts — 520 lux average achieved. Acoustic baffles complete in all zones — reverberation time confirmed at 1.1 seconds. Net storage system installed at perimeter wall.
Days 26–28
Net Posts, Scoreboard System, Soft Launch
12 net post pairs installed and tensioned to BWF height. Tournament scoreboard system mounted. Spectator gallery seating installed along the south wall. Soft launch on Day 27 — 60 invitations across 12 companies, all slots booked within 2 hours. Formal opening Day 28; first inter-company match played that evening.
Blue and Green courts taking shape, Day 14
Blue + Green courts taking shape — Day 14
All six courts complete under LED lighting, before net installation
All 6 courts under LED lighting — Day 23
Inter-company league match day, all six courts in use
Inter-company league match day — all courts in use
Want to see what this would cost for your space?
Get Estimate Call Now WhatsApp
THE RESULT
200+
Registered Active Players
12
Companies in the League
94%
Booking Slot Utilisation
2
New Tenants Cited the Facility
Weekday booking utilisation — 94% of all available slots
Lunchtime slots — 100% (waitlist in operation)
Employee awareness — 83% registered or waitlisted across 12 companies

The inter-company league started with eight teams. By the second season it had grown to twenty-four — two teams from each of the park's twelve companies. Saturday match days draw spectators from companies that have no team in that day's fixtures. The facilities manager has introduced a spectator queue for the finals. The same space that failed as a food court and a gym now operates with a waitlist.

Two new tenants — both technology companies who toured the park during lease negotiations — cited the badminton facility as a factor in their decision to sign. One HR director was direct: "When we are competing for talent with parks that have rooftop pools, having a proper six-court badminton complex is a genuine differentiator." The asset that sat empty for three years is now the most talked-about amenity in tenant conversations.

The facilities manager is now in discussion with the park committee about expanding into an adjacent space. Phase 2 is under consideration. The timelapse camera is still mounted to the same column. When the time comes, we know exactly how to set it up.

"We had tried every other use for that space. When we finally decided on badminton, it felt obvious — like we should have thought of it three years ago. The courts run at capacity every single day."

— IT Park Facility Manager
Project Location
Bengaluru, Karnataka
Sport: Badminton (x6 Courts) | Surface: PP Interlocking Tiles | Client: Corporate IT Park
Client IT park name and specific tenant companies have not been identified. Utilisation data and league participation figures were provided by the park facilities management. Lighting lux measurements were taken at handover by the park's MEP consultant. Acoustic reverberation data is from the independent specialist subcontractor's completion report. Product specifications and warranty terms are accurate as of installation date. All images and videos on this page are for representation purposes only and may not depict actual project sites.

Want a Court Like This?

Tell us about your space, your sport, and your timeline. We'll send you a detailed estimate within 48 hours — completely free.

  • Free estimate — no commitment
  • Written quote within 48 hours
  • Turnkey delivery across India

Prefer to call or WhatsApp?

Get Your Free Estimate

We respond within 24 hours. No spam, no pressure.