A Cricket Pitch Between the Buildings

Aerial view of the narrow space between two corporate campus buildings where the cricket practice pitch would be built, Mysore
60 ft wide. 70 ft long. Buildings on both sides. No vehicle access from any angle. Most vendors said it was impossible. We said it was a pitch.

Aerial view is representative. Drone photography of the actual completed installation pending client approval.

Mysore Karnataka
4,200
Square Feet Total
12
Days, All Manual Delivery
PP + Turf
Dual Surface System
8
Corporate League Teams
2
Practice Nets (Both Ends)
Diwali
Corporate Trophy Tournament
THE CHALLENGE

The recreation committee had spent three months trying to find space on the campus for a cricket practice facility. Every open area was already taken — parking, landscaping, a generator yard that no one wanted to touch. The HR head was about to push the idea to the next quarter when the committee chairperson noticed the strip.

The strip ran between Block A and Block B, the two original buildings on the campus. Sixty feet wide, seventy feet long. Both long sides were the actual facade walls of occupied office buildings. The short ends had ornamental hedging. There was zero vehicle access from any direction — the gap between the building corners and the perimeter boundary was too narrow for a loaded flatbed, and campus management had already said no to removing any section of hedge. All material would have to be hoisted over the building wall from the public road outside using a mobile crane, then carried the rest of the way by hand.

Three quotes were obtained. Two vendors visited, saw the access situation, and backed out within the week. The third sent a quote so loaded with logistics surcharges it was unbudgetable. The recreation committee chairperson sent the requirement to ChampCourts with a note that said, in part: "Every other vendor says it cannot be done. We believe it can. We are looking for someone who agrees."

ChampCourts agreed. The site visit confirmed the constraints but also identified the opportunity: the existing concrete walkway in the strip was in good structural shape. No demolition. No base construction. No concrete work inside the site at all. The project was purely a surface installation. Turf rolls could be carried once they were over the wall. Infill material came in bags. The PP tiles for the run-off surround were 1ft x 1ft — man-portable in any quantity. Every element of the scope had been chosen to travel by hand.

Artificial turf roll being hoisted by mobile crane over the corporate campus boundary wall
Day 1 — first turf roll hoisted over the boundary wall. The crane operator called the gap "barely visible from the road." By Day 3, he was calling every morning to confirm his schedule — he wanted the shift.
THE SOLUTION

The specification was a dual-surface system: a central artificial turf pitch strip of standard cricket practice dimensions, with a PP interlocking tile surround for the run-off area at both ends. This combination serves the two distinct functions of a practice facility. The turf strip provides the consistent bounce and pace response that batting and bowling practice require. The PP tile surround gives a stable, level surface for players waiting, coaches observing, and fielders retrieving — a harder surface that handles foot traffic at the edges far better than turf does.

A 35mm pile-height non-directional cricket turf was specified for the pitch strip. This pile height performs consistently for both pace and spin bowling and does not create the artificial pace variation that would mislead batters during training. White crease markings were inlaid directly into the turf using contrasting white fibre sections rather than painted on — a durable finish that survives heavy foot traffic and repeated ball strikes without wearing away.

Practice nets at both ends allow two simultaneous sessions — bowlers running up toward each net, batters at each end, no conflict between sessions. The net poles were specified as sectional galvanised steel — each section man-portable — drilled into the existing concrete with chemical anchors. No concrete footings, no base plates, nothing that required any wet work inside the site.

Artificial Turf — 35mm Pile, Cricket Green PP Interlocking Tiles ₹70/sqft — Run-off Surround White Crease Inlay (Not Painted) Silica Sand + Rubber Crumb Infill Practice Nets Both Ends — 4.5m Height Sectional Galvanised Net Poles All-Manual Site Logistics No Vehicle Access Required
Planning a Similar Cricket Pitch?
Tell us about your space, sport, and timeline. We'll send you a detailed estimate within 48 hours — completely free.
Get Free Estimate WhatsApp Us
Free estimate • No commitment • Response within 48 hours
THE BUILD

The crane was on the public road at 6 AM on Day 1, before office hours. Campus security had coordinated two access windows — one early morning, one in the evening — where the road-side crane operation would not block working traffic. Between those windows, the crew worked entirely within the site using material already hoisted in. Twelve days of this: hoist in the morning, install through the day, hoist again in the evening.

Day 1
First Hoist + Site Setup
Mobile crane positioned on the public road. First four turf rolls, all infill bags, and the PP tile pallets for the surround area hoisted into the strip across two morning windows. Everything man-carried from the drop zone. Concrete surface swept, pressure-washed, and allowed to dry. Reference lines marked for the central turf strip and PP tile surround zone.
Days 2–3
Concrete Surface Prep + First Turf Rolls Laid
Existing concrete walkway: low points filled with rapid-set mortar, expansion joints sealed with flexible compound to prevent future turf undulation. First turf rolls laid and glued to the perimeter bond line, direction verified against the pitch axis. Seams between rolls glued with polyurethane turf adhesive and weighted for a 48-hour cure. PP tile surround started at both short ends simultaneously.
Days 4–7
Full Turf Installation + Infill + PP Tile Surround
All turf rolls laid, seams cured and inspected. Silica sand infill brushed in by hand broom — the power broom had been partially disassembled to fit through the hoist sling and was reassembled on site. Rubber crumb infill followed. Pile direction checked across the full playing surface. PP tile surround laid across both end run-off zones, snapping into place from the turf edge outward to the building wall.
Days 8–9
Crease Inlay Markings
Batting crease, popping crease, and return crease installed at both ends using white fibre inlay strips set into pre-cut turf sections. Crease positions measured to MCC standard before cutting — an error here cannot be undone without replacing a full turf section. Markings installed perfectly on the first attempt at each end. No paint. No masking tape. The inlay is structural, not cosmetic.
Days 10–11
Practice Net Poles + Netting
Sectional galvanised poles drilled and chemically anchored at both ends — four poles per net enclosure. Frame assembled section by section inside the strip, each piece walked in by hand. Heavy-duty polyethylene netting fixed at 4.5m height and tensioned. Safety padding applied to all pole bases within the batting zone. Net tensioning checked with a test ball before signing off.
Day 12
Infill Top-Up, Final Brushing & Handover
Final infill top-up and power brushing to stand the pile evenly. Ball-bounce test at six points across the pitch strip — pace and rebound checked against a reference bounce on a known-good turf surface. Consistent across all six points. Handover walk-through with the recreation committee chairperson and the HR head. First ball bowled that afternoon — a full over of medium-pace from the committee chairperson who had been waiting twelve days to do exactly that.
PP interlocking tiles being installed in the run-off surround area around the pitch strip
Day 5 — PP tile surround going in at the batting end. The tiles meet the turf strip edge with a clean kerb line. No adhesive, no grout — purely interlocked.
White fibre crease inlay being set into the artificial turf pitch strip
Day 8 — crease inlay installation. White fibre set into the turf, not painted over it. This will not fade, flake, or wear off with repeated ball impact and foot traffic.
Practice nets at both ends of the cricket strip installed and tensioned
Day 11 — both net enclosures up and tensioned. Two simultaneous sessions are now possible. The buildings on both sides also happen to block crosswind — an accidental advantage.
Completed cricket practice pitch between the two buildings on Day 12
Day 12 — done. 4,200 sqft of cricket infrastructure between two buildings that most contractors said would not allow it. The buildings did not move. We worked around them.

All images are illustrative placeholders. Final installation photographs and drone footage pending client approval.

Want to see what this would cost for your space?
Get Estimate Call Now WhatsApp
THE RESULT

The weekend cricket that had been happening at a rented ground six kilometres away shifted on-campus within a fortnight of handover. The commute had been the main reason participation was low — a 45-minute round trip in Mysore weekend traffic, added to what was supposed to be a lunch-hour or after-work session, made recreational cricket feel like a commitment most employees could not sustain. On-campus, the strip is a four-minute walk from any desk in either building.

Eight teams formed within two months. Enough for a structured league, which the recreation committee organised with minimal effort — one spreadsheet, one WhatsApp group, a shared calendar for the pitch. The Diwali corporate trophy was the first formal tournament, a round-robin across all eight teams, with the final played under emergency site lights borrowed from the facilities team. The recreation committee chairperson presented the trophy. He was also the one who had spotted the strip in the first place.

The weekday evenings filled up too. Informal bowling sessions in the practice nets after office hours, no organisation needed — people simply went there. The HR head, who had approved the project budget against some pushback from the finance team, presented the participation numbers at the following board review. Sports infrastructure, it turned out, was also a retention argument.

A Strip No One Thought Was Possible. A Pitch Everyone Uses.
8
Corporate Teams in Structured League
12
Days, Zero Vehicle Access
Diwali
First Corporate Trophy Tournament
2
Simultaneous Practice Net Sessions
Project delivered in 12 days with all-manual site logistics
Net utilisation at 60 days — 72% of available evening hours in active use
Sports participation increase on campus — 60% growth vs. pre-installation quarter

"Three vendors said it was not possible. I genuinely could not understand why — the space was there, the ground was solid, and people wanted to play. All that was missing was someone willing to figure out the logistics."

Office Recreation Committee Head, A Technology Campus, Mysore
Product specifications: PP Interlocking Tiles at ₹70/sqft (supply). Artificial turf pricing varies by pile height and specification — contact us for a project-specific assessment. 5-year warranty on PP tiles; artificial turf warranty subject to product specification. Court dimensions are custom to site. All project details shared with client approval. Company name and campus details withheld at client request.

Want a Court Like This?

Tell us about your space, your sport, and your timeline. We'll send you a detailed estimate within 48 hours — completely free.

  • Free estimate — no commitment
  • Written quote within 48 hours
  • Turnkey delivery across India

Prefer to call or WhatsApp?

Get Your Free Estimate

We respond within 24 hours. No spam, no pressure.